loading...

. . . . . .

let’s make something together

Give us a call or drop by anytime, we endeavour to answer all enquiries within 24 hours on business days.

Find us

PO Box 16122 Collins Street West
Victoria 8007 Australia

Email us

info@domain.com
example@domain.com

Phone support

Phone: + (066) 0760 0260
+ (057) 0760 0560

VC Summer Construction Update

  • By Admin
  • May 10, 2017
  • 350 Views

In its latest progress report to the state’s Public Service Commission, South Carolina Electric & Gas Company released their 1st quarterly report for 2017 stating that the VC Summer nuclear construction project is now over 64% complete.  The substantial completion dates for the two AP1000 units are currently unchanged from previous timelines but are to be re-evaluated in light of Westinghouse’s recent bankruptcy filing.  Currently the units are targeted for completion in April 2020 for unit 2 and December 2020 for unit 3.

 

Completion Percentages

 

 

% Complete 4th Quarter 2016

% Complete 1st Quarter 2017 % Change
Engineering 94.9% 96.0% +1.1%
Procurement 84.6% 88.2% +3.6%
Construction 30.9% 34.3% +3.4%
Start-up 7.7% 8.6% +0.9%
Total 60.9% 64.1%

+3.2%

 

Click here to read the entire report for Quarter Ending March 31, 2017

Leave a Reply

Your email address will not be published.