VC Summer Construction Update

  • By Admin
  • May 10, 2017
  • 472 Views

In its latest progress report to the state’s Public Service Commission, South Carolina Electric & Gas Company released their 1st quarterly report for 2017 stating that the VC Summer nuclear construction project is now over 64% complete.  The substantial completion dates for the two AP1000 units are currently unchanged from previous timelines but are to be re-evaluated in light of Westinghouse’s recent bankruptcy filing.  Currently the units are targeted for completion in April 2020 for unit 2 and December 2020 for unit 3.

 

Completion Percentages

 

 

% Complete 4th Quarter 2016

% Complete 1st Quarter 2017 % Change
Engineering 94.9% 96.0% +1.1%
Procurement 84.6% 88.2% +3.6%
Construction 30.9% 34.3% +3.4%
Start-up 7.7% 8.6% +0.9%
Total 60.9% 64.1%

+3.2%

 

Click here to read the entire report for Quarter Ending March 31, 2017